  • Redirected/Rejected Waste Loads


    Lessons learned following a rejected inert waste load which was redirected after being found to contain fibrous material and hydrocarbons.

    Download 16.8.2017
  • Consent Condition Challenges on Heavily Polluted Site


    At the affected site, higher than anticipated quantities of groundwater and ground contamination levels resulted in a number of challenges in meeting the consent conditions.

    Download 16.8.2017
  • Storage of Potentially Harmful Liquids on IBCs


    When storing chemicals on intermediate bulk containers (IBCs), ensure that a bund is used which exceeds the capacity of the IBCs.

    Download 16.8.2017
  • Pipe Fitting Impact - Hand Fracture


    Lessons learned following a RIDDOR reportable hand fracture while handling a 4" section of unlined cast iron water main.

    Download 16.8.2017
  • Working in Live Traffic


    Lessons learned following the observation of a traffic management supervisor working in live traffic lanes without taffic management in place.

    Download 8.8.2017
  • Excavator Overturned


    Lessons learned from an excavator which overturned while lifting on un-compacted ground.

    Download 8.8.2017
  • Site Establishment and Management of Pedestrian Routes


    The injured person obtained a RIDDOR reportable injury when tripping on a piece of plywood placed under rubber matting. This document outlines the steps which can be taken to prevent a recurrence.

    Download 8.8.2017
  • Management of Pedestrian Routes


    A RIDDOR reportable incident occurred following a slip while the injured person was stepping up onto a kerb.

    Download 8.8.2017
  • Use of Trench Boxes


    An incorrectly fitted trench box was prematurely removed, leading to the partial collapse of an unsupported excavation which had been deemed as needing support, resulting in an injury.

    Download 8.8.2017
  • Struck by Object


    Structures can move over time, changing the way that energy is stored. When dismantling, look for indicators of stored energy, ensure a robust weekly inspection regime is in place and alsways consider 'line of fire' consequences.

    Download 8.8.2017
  • Securing of Scaffolding Boards


    A reminder not to underestimate the power of the wind, and guidance on ensuring that boards are secured rather than restrained, following an incident where a tube was installed to fill a gap in the deck.

    Download 7.8.2017
Toolbox talks
  • Dumper Striking Building

    Lessons learnt bulletin: Dumper striking existing STW admin building at Kilburn STW. A 6 Tonne Dumper was being used to take a compressor to the side of the iold admin building. Whilst carrying out the operation the operator struck the building with the rear of the dumper causing some structual damage.

    Download 18.09.2017
  • Chalk/Calcium Carbonate Discharge

    This document is an environmental lessons learnt from a recent incident on site

    Download 25.11.2016
  • Lessons Learnt - Manor Road

    This document provides a summary of necessary actions that should be taken in the event of a regulator coming to site.

    Download 25.11.2016
  • Whacker Near Miss

    HSBulletin017 Whacker Near Miss

    Download 30.08.2016
  • Visual Inspection before Invesigation

    Thorough Visual Inspection before Investigation

    Download 30.08.2016
  • Site Inspection

    IA SHE08 Site Inspection Checklist Requirements for entry direct to RIVO

    Download 30.08.2016
  • Incident Reporting

    Update & outline of requirements for Incident Reporting & Incident Investigation Document Suite

    Download 30.08.2016
  • Services encased/surrounded by concrete

    Services encased or surrounded by concrete

    Download 30.08.2016
  • 24 Hour Incident Line

    24hr Incident Line

    Download 30.08.2016
  • Gas Service Strike

    Gas Service Strike

    Download 30.08.2016
Show more
 

Email this Document

Thank you

Your email has been sent